The two yards of the New England Shipbuilding Corporation - the East and
the West - commenced operations under different titles and until early
1942 were separated by rigid legal conditions.
The origins of the East yard date from 1941, for in that year two
American concerns contracted to build 'Ocean' type ships for British
account. One such concern was the Todd-Bath Iron Shipbuilding Corp.,
whose new yard of the dry dock (or basin) type was situated on the edge
of a residential community to the east of Cushing Point, South Portland,
Maine. Here, launchings were not down slipways; instead the basins were
flooded and the ships were floated out.
West Yard
While this yard was still under construction the management was
instructed by the Maritime Commission to build another new yard next to
it. Situated to the west of Cushing Point, it was to be operated by the
South Portland Shipbuilding Corporation and became known as the West
yard. After Pearl Harbor the restrictive legalities of the separate
yards were swept aside and both yards were operated as one enterprise by
this corporation.
The Todd-Bath Corporation, when building the 'Ocean' ships, carried out
much of the steel fabrication at the new plant of the Bath Iron Works
(the parent company of both these South Portland yards) and which, owing
to the lack of local expansion facilities, was situated some 30 miles
away from the shipyard. The East yard, therefore, was given no great
fabricating or assembling areas.
The construction of the four-way West yard was more orthodox, the ships
being launched from normal slipways. As a four-way yard it seemed ideal
but the increase to six slips was really more of a contraction than
expansion, for there was then no additional space and the extra slips
just had to be fitted in with the others. However, all the materials
for their construction had to be taken across the four original ways,
and this greatly interfered with the shipbuilding activities.
Here also, the layout failed to include fabricating shops, the intention
again being to have this work carried out by Bath Iron Works and thence
carried by road from the nearest railhead, some three miles away. But
production by this method was too slow and when the call came for an
all-out effort these plans were of little use. In March 1942 the
commission took an active part in providing the facilities to enable
ships to be pre-assembled in large units instead of being put together
piece by piece.
Soon the inhabitants of Cushing Point found the two shipyards
encroaching into their community and condemnation of property became
commonplace as expansion demanded fabricating shops, housing for the
workers and even a railroad. During the summer of 1942 eviction and
demolition proceeded rapidly but long disputes and troubles over
construction, supervision, facilities, fees and management all ensured
that the deliveries of ships from the first contract were very much
delayed. In fact, after the first Liberty keel was laid in September
1942 the East yard found itself building in some of its basins for
British account and in the others for the Maritime Commission.
Collectively however, the delays were so great that the Commission
contemplated termination of the agreements by default, but their bitter
experiences at Savannah (see Southeastern Shipbuilding Corp.) indicated
the wiser course of a negotiated settlement. So, in early 1943 - at which
time the yards had been without a clear authority for nearly a year
- Todd Shipyards Corporation took over control from Bath Iron Works and
installed new management 'on trial' for a period of sixty days. During
this time the two yards, now with the New England title, were expected
to fabricate and erect 36,000 tons of steel and to deliver twelve vessels.
By March 1943 their performances were considered by the Commission to be
satisfactory, and soon after further expansion occurred with the
acquisition from the US Navy of land to the north of the area. These new
shipbuilders, who were never one of the fastest yards and were in
fact one of the two slowest, nevertheless considerably reduced their
total number of manhours per ship. Over a two-year period commencing in
May 1943 the figure dropped from 760,000 to 410,000, and after many
early troubles the yard finally constructed an excellent number of
vessels.
Liberty ship output (both yards): 236 vessels at an average cost of
$1,892,000 each, plus 8 for the transport of boxed aircraft.
Vessels built at the East Yard:
| USMC Numbers | Yard Numbers |
| Built by Portland Shipbuilding Corp |
| 761-792 | 252-276, varied order |
| 814-815 | 231-239 |
| 820-821 | 244-245 |
| 823-824 | 247-248 |
| 827 | 251 |
| Built by New England Shipbuilding Corp |
| 793-800 | 277-284 |
For the remaining constructions at this yard the MCE number was used as the yard number.
Vessels built at the West Yard:
| USMC Numbers | Yard Numbers |
| Built by South Portland Shipbuilding Corp |
| 201-213 | 201-213 |
| 333-338 | 217-222 |
| Built by New England Shipbuilding Corp |
| 214-216 | 214-216 |
| 339-340 | 223-224 |
| 801-813 | 225-237 |
| 816-819 | 240-243 |
| 822 | 246 |
| 825-826 | 249-250 |
For the remaining constructions at this yard the MCE number was used as the yard number.
World War II Construction Records of the New England Shipbuilding Company
Production Records of the New England
Shipbuilding Corp.
History of the
South Portland Shipyards.
Portland's Liberty Ship Era
The South Portland Shipyard Oral History Project, supported by Portland radio station WMPG-FM and the Portland
Harbor Museum, created an oral documentary by recording the recollections of World War II Liberty shipyard workers
and local residents. Listen to their stories.