In the United States, in January 1942, there occurred a sudden need for
additional shipyards for the construction of major types of ships to
meet an increase of one-third in the previous objectives. One of these
new yards was set up by the Kaiser group at Vancouver, across the
Columbia River from Portland, Oregon, and in the following month the
decision was taken to increase the original plans to a total of twelve
slipways.
The yard was constructed on land owned by the local ports authority; it
was leased at the nominal fee of $300 per year, and the final
terms of leasing required the premises to be restored to 'as good a
condition as before.'
In mid-1942, with the yard itself still under construction, the first
ship on the stocks and the local labor supply almost exhausted, a big
recruiting drive was directed not only to the mid-West and to the
mountain states, but even to places as distant as New York. The
subsequent influx of personnel tended, at first, to outstrip the
available facilities and one service the commission was forced to
provide was a private railway to carry workers to the shipyard.
The yard was awarded a large contract for Liberty ships, but soon this
was changed to one for military types. More than a hundred Liberty
contracts were cancelled and this gave a large surplus of Liberty
material, which was transferred to the Oregon shipyard. Nevertheless,
included in the yard's facilities was a 'deckhouse' slip, situated
between the slipways and the outfitting dock. Thus, while in transit
between these two points, ships would pause to have previously completed
210-ton deckhouses installed. The deckhouses were complete, even to the
installation of the funnel, before they emerged for fitting. This
system, in fact, set another trend in assembly line methods, but was of
no real importance to the Liberty program, being mainly used on
military constructions. It also gained unfavorable publicity when, in
October 1942, the first deckhouse assembly was accidentally dropped twenty
feet onto a waiting hull!
The first of the military types (LSTs), were ordered in May 1942 and
for these new buildings the yard ceased work on Libertys after launching
and completing only two and clearing away two more that were only
half-built. Immediately afterwards fifty escort carriers were ordered,
yard facilities were again improved and it became one of the best
emergency yards in both its equipment and its layout.
In early 1943 the yard was able to revert to Liberty building long
enough to construct eight more vessels, but with these ships the
propelling machinery was installed at Portland by the Oregon
Shipbuilding Corporation. Later still the yard turned its production to
military transports.
After the war the leasing arrangements were revised and the yard became
one of the Maritime Commission's four stand-by yards for use in future
emergencies. In 1960 it was sold to the Gilmore Steel Corporation for some
$3 million.
Liberty ship output: 10 vessels.
| USMC Numbers | Yard Numbers |
| 353-356 | 1- 4 |
| 357-392 | cancelled |
| 393-400 | 41-48 |
World War II Construction Records of Kaiser Company, Vancouver, Washington